When adjusting the slider to allocate resources for a Resource Pool, the yellow indicator on the resource bar indicates?
A. A warning flag set at 75% of the remaining available resources
B. the remaining resources available
C. the recommended resource amount
D. the minimum required resource amount
Answer: B